15/08 Brick work on tie beams

15 August 2011



Posted by chait2000 at 6:35 PM

10/08 After concreting of tie beams

10 August 2011




Posted by chait2000 at 6:30 PM

06/08 Concreting of tie beams

06 August 2011





Posted by chait2000 at 6:25 PM

27/06 to 21/07 Concreting of foundation beams

27 June 2011 to 21 July 2011






27-30 June 2011











Posted by chait2000 at 6:19 PM