Protection Apartments
Monday, June 13, 2011
12/06 Starting of Column Work
12 June 2011
Saturday, June 11, 2011
10/06 Foundation (pits 3 of 9 completed): beams soaked in water for curing
10 June 2011
09/06 Laying of concrete in the foundation beams
09 June 2011
02/06 Commencement of foundation work
02 June 2011
01/06 Digging pits for the foundation
01 June 2011
25-26/05 Site measurement and marking of column positions
25-26 May 2011
15/05 Demolition of old building
15-20 May 2011
24/04 Bhoomi Pooja
24 April 2011